Method

The reference data behind a tender price: consumption standards, material data and the rate build-up.

Cement consumption by concrete grade

bags / m³ · two published references

Source ASource B

bags / m³

  • M-15

    5.906.27
  • M-20

    6.907.00
  • M-25

    7.508.50
  • M-30

    8.009.20

The standard references disagree grade by grade. Which one your estimator starts from changes what you buy.

The unit rate, built up

per BOQ line

  1. Material

    take-off quantity × current supplier rate, per material behind the line

  2. Wastage

    allowance on the material, set per trade

  3. Labour

    crew cost against the output norm for the item

  4. Plant

    equipment time the item consumes

  5. Overheads & margin

    prelims, running cost and the number you defend

8″ masonry block, data sheet

400 × 200 × 200 mm · Dubai spec

PropertyHollowThermal (insulated)
Weight~22.5 kg~23.6 kg
Density~1,320 kg/m³two leaves + core
Mean compressive strength~7.5 N/mm²spec-dependent
Insulation corenone (two cavities)60 mm polystyrene
U-valueuninsulated~0.48 W/m²·K
Thermal conductivityn/a~0.11 W/m·K

The premium buys the core: on an envelope wall the insulated block usually wins once the cooling load is priced.